Going Agile: 2 Weeks On The Life Of a Scrum Team

The Ubuntu Certification team is fully distributed and has now been running Scrum for over 9 months. The team has members in Canada&US, Europe and Asia. I have been blogging about several parts of our scrum experience, now is time to piece it all together!

We run in 2 week iteration cycles within a larger 6 month release cadence. Here is what those two weeks look like:

Day1 (Thursday)- Planning session

We run the planning session (30 minutes) just after the previous iteration Demo session – No room to breath! The reason for doing this is just down to timezone and trying to get as many people as possible into this sessions.

We host the planning session in Mumble, and we review the backlog for the next iteration. We found it a bit dull just for the Product Owner to explain what each story was about. Instead, we ensure that everyones participation by agreeing the definition of done for the stories. This eliminates any misunderstandings of what needs to be deliver and ensure that everyone is paying attention.

Just after the planning session, the scrum team gets together to flesh out the task-board for the iteration. At this point the stories are re-size via IRC planning poker: At the count of three by the Scrum Master every one pastes a t-shirt size on the IRC channel.

Following the poker planning, the team discusses possible implementations and they write down tasks in the IRC channel, to be later translated by the Scrum Master into the backlog.

Daily Scrums

We run two scrums (no longer than 15 minutes) a day. A reduced one at 9.30 UK time with Europe and Asia, and a larger one at 15.00 UK time including UK and US. We run both using Mumble but Google+ is also a good option.

Day 5 (Wednesday) – Backlog review with the Scrum Master

On Wendnesday, Ara and I review the progress of the backlog and discuss any stories that might need to be refocused, unblocked or delayed to a later iteration.

Day 6(Thursday) – Discussing impediments and new ideas

At this point, we have reach the equator of the iteration. We host a 45 minutes meeting following the main scrum to talk about any issues the team wants to raise. This mainly focuses around problems facing our work or new ideas for future iterations or releases.

Also, the Scrum Master send an mid-iteration status email. This ensures that nothing is falling through the cracks and everyone knows the overall iteration progress. We find that scrums tent to focus on what people are working and not what is left in the backlog, this can lead to lower priority user stories being worked on while higher importance ones remain overlooked.

Day 9 (Tuesday) – Backlog review for next iteration

The Scrum Master, Product Owner and I get together to review what stories are likely to not be completed. This is normally 80% accurate and gives us a better idea of how many new stories are to be added for the next iteration. Then, we discuss priority of stories and we create a draft backlog for the next iteration. Although there are always  changes during the planning session, this gives us a solid draft to start from.

Day 11/Next Day 1( Thursday) – Demo

We completed the full circle and we are back at the demo and planning meeting, where a demo lead shows via Spreed (screen sharing tool) what has been achieved.

About these ads

2 Responses to Going Agile: 2 Weeks On The Life Of a Scrum Team

  1. Pingback: Going Agile: Scrum or Kanban? « Going Agile

  2. Pingback: Going Agile: Scrum or Kanban? « Victor Palau's Blog

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.

%d bloggers like this: